The Tennessee Department of Transportation has announced a variety of road construction projects through March 9 across Williamson County and Middle Tennessee:

  • The repair of the bridges on I-840 over South Garrison Branch (MM 15.2–17.4) will take place 24/7 with long term lane closures on I-840 in both directions for bridge approach slab work. One lane will remain open in each direction.

  • Grading, drainage and paving work on State Route 6 (Franklin Road) from south of Moore's Lane (LM 15.93) to Concord Road (18.53) – (mm 15.93 – 18.53) will take place daily from 9 a.m.-3 p.m.

    Intermittent stoppages of traffic and/or temporary lane closures are to be expected (one direction at a time) for various construction activities and utility work throughout the project.

    There will be extended delays and possible lane closures for utility operations for the following side roads: Ashby, Drive, Holly Tree Gap Road, Long Street, West Concord, Wikle Road and Mt. View Road.
  • Grading, drainage, construction of bridges and signals on State Route 96 from east of Arno Road (LM 14.72) to State Route 252 (Wilson Pike - LM 20.62) will take place daily from 9 a.m. to 3 p.m. There will be lane closures and brief stoppages of traffic for utility relocations and grading work.

  • The replacement of a 60" corrugated metal pipe on US 431 (SR 106) at MM 13.65 will see a continuous full road closure on State Route 106 (Lewisburg Pk) between Carnton Lane and Eastern Flank Circle until June 30 for culvert replacement.

    Traffic will be detoured via State Route 6 (Columbia Ave) and State Route 397 (Mack Hatcher Parkway). Detour signs will be in place.

  • Grading, drainage, construction of bridges, retaining walls and paving on SR 397 (Mack Hatcher Parkway) from south of State Route 96 to east of US Highway 431 (State Route 106) will take place daily from 9 a.m.-3 p.m.

    There will be temporary lane closures in both directions on Mack Hatcher at Hillsboro Road and also on Hillsboro Road northbound.

  • In addition, TDOT is working on multiple large-scale emergency pothole repair projects throughout the region, but none of those specifically impact Williamson County roadways.